Pre-award memo · TR-2026-0042SAMPLE DATA

Contract I-26-4877 — Roadway resurfacing, I-88 EB

Generated Aug 21, 2026 · 7:04 AM Trigger Scheduled run Source Illinois Tollway public records, 2015–2026
The low bid holds after adjustment.
Fox Valley Roadbuilders Bid № 1Adjusted № 1
Bid
$12.4M
Historical growth
+4.5%
median +4.5%
Adjusted cost
$13.0M
Record
4 contracts
$88M awarded → $92M authorized

Recurring cause of growth: design changes — 2 of 4 contracts.

I-24-4845 · Res. 24270 · +$700,000Source
"material price adjustment for hot mix asphalt"
I-20-4440 · Res. 21930 · +$610,000Source
"asphalt price escalation per contract special provision"
Prairie State Infrastructure Bid № 2Adjusted № 2
Bid
$13.1M
Historical growth
+15.0%
median +14.5%
Adjusted cost
$15.1M
Record
6 contracts
$96M awarded → $110M authorized

Recurring cause of growth: design changes — 5 of 6 contracts.

I-23-4790 · Res. 23688 · +$2,140,000Source
"revised plans for shoulder widening at the ramp terminals"
I-22-4700 · Res. 23001 · +$1,980,000Source
"redesign of drainage structures following plan omission"

Limitations. Growth is computed from the agency's own published award and authorized amounts. Stated reasons are quoted verbatim from board resolutions, which are written to obtain approval and reflect the agency's own framing. Increases absorbed within contingency or below board approval thresholds never appear in public documents and are not counted here. This memo supplies a missing variable; it is not a recommendation.