Meridian Heavy Civil
Bid № 1Adjusted № 2
Historical growth
+9.0%
median +7.4%
Record
12 contracts
$312M awarded → $340M authorized
Recurring cause of growth: unforeseen underground conditions — 6 of 12 contracts.
I-19-4390 · Res. 21106 · +$2,215,000Source
"utility relocation conflicts requiring redesign of storm sewer alignment"
I-21-4512 · Res. 22471 · +$1,840,000Source
"to provide for underground obstruction removals encountered during caisson installation"
I-24-4855 · Res. 24102 · +$1,560,000Source
"differing site conditions in the west abutment excavation"
I-23-4760 · Res. 23611 · +$1,405,000Source
"removal of buried foundations not shown on the contract plans"
I-18-4301 · Res. 20544 · +$1,120,000Source
"differing site conditions at pier foundations requiring rock excavation beyond plan depth"
Lakeshore Constructors
Bid № 2Adjusted № 1
Historical growth
+2.1%
median +1.8%
Record
8 contracts
$205M awarded → $209M authorized
Recurring cause of growth: materials and pricing — 3 of 8 contracts.
I-22-4718 · Res. 23054 · +$610,000Source
"structural steel price escalation per contract special provision 109.04"
I-19-4372 · Res. 21044 · +—Source
"extension of time due to winter shutdown, no additional cost"
I-23-4802 · Res. 23820 · +—Source
"fuel and material price adjustment per published index"
I-21-4560 · Res. 22610 · +—Source
"railroad coordination delay at the Union Pacific crossing"
I-20-4455 · Res. 21902 · +—Source
"asphalt price adjustment per special provision, no additional contract time"
Calumet Bridge & Iron
Bid № 3Adjusted —
Insufficient history.
2 comparable prior contracts found. Track Record does not
compute growth from fewer than 3, so this bidder appears
in the bid ranking only.